April 13th
Team Charters
April 27th
Team WBS that includes work and time estimates
Material and equipment list for the teams work. This list should indicate each item, quantity, type, style, etc. and will be used for budget allocation purposes.
Initial project network
Financial status report
May 4th
1st draft SOW
Pre-project plan
Quality and performance standards and procedures must be proposed - responsibilities, timing of quality checks, means of communication and resolving quality problems.
May 6th
SOW to class
May 9th
Final material and equipment list
Financial status report
Scope adjustment
May 11th
Project plan presentation - must include responsibility matrix and set up task for each day and project closeout plan.
Project risk assessment and contingency plans
Final quality assurance and safety plans - consolidation and reconciliation of inputs from various work teams.
Make sure everyone knows what they are doing
May 14th-15th
Work the Plan
May 16th
Status report for work weekend
Adjustments as needed.
May 18th
Project plan update/adjustments for second weekend - must include responsibility matrix
Final preparation and review of responsibilities.
Make sure everyone knows what they are doing for second weekend
May 21st-22nd
Work the Plan