Tentative Plan 2006


April 13th
• Team charters

April 27th
• Team WBS that includes work and time estimates
• Material and equipment list for the teams work. This list should indicate each item, quantity, type, style, etc. and will be used for budget allocation purposes
• Initial project network
• Financial status report

May 4th
• 1st draft SOW to instructor
• Pre-project plan
• Quality and performance standards and procedures must be proposed ? responsibilities, timing of quality checks, means of communicating and resolving quality problems

May 9th
• SOW to class
• Project risk assessment and contingency plans
• Final material and equipment list
• Final quality assurance and safety plans ? consolidation and reconciliation of inputs from various work teams
• Financial status report
• Scope adjustment

May 10th
• Project plan presentation ? must include responsibility matrix and set up task for each day and project closeout plan
• Make sure everyone knows what they are doing

May 13th-14th
Work the Plan

May 16th
• Status report for work weekend
• Adjustments needed

May 18th
• Project plan update/adjustments for second weekend ? must include responsibility matrix and set up task for each day and project closeout plan
• Make sure everyone knows what they are doing for second weekend

May 20th -21st
Work the Plan